A Columbia (Ky.) firm is building a new plant to supply concrete for the barrier wall to be inserted into leak-plagued Wolf Creek Dam.
A spokesman at Pyles Concrete Inc. confirmed that his company is building the plant. The new facility is located across U.S. 127 from the entrance to Lake Cumberland State Park about 3 miles north of the dam.
Larry Craig, power plant manager at Wolf Creek Dam, said work on the concrete plant has been going out for about six weeks. The plant should be ready to supply concrete for widening the work platform on the upstream side of the dam. This project will be done very soon by Weddle Enterprises of Somerset.
Meanwhile, the lake is nearly back to its target of 680 feet above sea level after being flushed by heavy rains to about eight feet above an acceptable range. All six generators in the dam operated for several weeks to get the lake to where the U.S. Army Corps of Engineers has tried to keep it for the past two years.
The lake at 6 a.m. Monday was 680.41 feet above sea level and falling slowly. Only one generator was operating, releasing 3,420 cubic feet of water per second into the Cumberland River below the dam.
Another storm system was approaching the area Monday and weather forecasters are predicting up to 3 inches of rain in the Cumberland River Basin. Runoff from rainfall in this amount could flush rivers and streams and trigger another rise in the lake.
Meanwhile, work at Wolf Creek Dam goes on. Treviicos-Soletanche JV, the joint French-Italian general contractor for the barrier wall project, is installing piezometers (pressure-reading instruments) atop the dam and Boart Longyear, another contractor, is installing piezometers on the downstream side of the dam. Craig said the northbound lane of U.S. 127 atop the dam is blocked for more than 500 feet while instrumentation is being put in place.
A $341.4 million contract was awarded last summer to Treviicos Soletanche JV to place a second concrete diaphragm in Wolf Creek Dam to stop uncontrolled seepage that has plagued the dam since Lake Cumberland was impounded.
The concrete barrier wall is the primary element of the Wolf Creek Dam Seepage Rehabilitation Project. The wall will be a combination of secant piles and rectangular panels installed through the earthen embankment to a depth of about 275 feet.
Extending the wall deep into the limestone formations beneath the dam will effectively cut off seepage through the structure. The wall will extend eastward along the upstream embankment from the concrete section to the right abutment, a length of about 4,200 feet.
Rehabilitation of the dam will be basically complete when the barrier wall is inserted. The four-year contract, if completed on time, would put the finish date in 2012, some two years earlier than had been projected.
Local News
Columbia firm building plant to supply concrete for dam
Reports indicate lake levels back to 680 feet
- Local News
-
- Trial delayed for parents charged with trafficking daughters
-
Wolf Creek Dam renovation on target for Summer 2014 completion date
-
Burnisde may soon move to fourth-class status
-
McGaha didn’t approve farewell letter
-
Refinery to re-open in early summer
- Downtown road work running ahead of schedule
-
Board upholds principal’s demotion
-
Fast-moving blaze guts mobile home off Slate Branch Road
-
Big Bang Theory
Pulaski County is not at war. The booming you may hear at dusk is mock cannon fire to scare away birds.
Stuart Spillman, environmental director for the Lake Cumberland Health Department, said at least three cannons are on loan from the department to residents who want to scare away swarms of starlings and blackbirds settling in to roost.
He said a cannon is being used by a resident on Laura Lane off Ky. 39; another is in the Oak Hill Road area and a third is on Ashurst Street in the eastern part of Somerset.
Spillman said a timer on each cannon allows it to “fire” at whatever frequency is desired. The cannons must be used as the birds circle before going to roost. “After they settle in, nothing will chase them out,” Spillman said.
The Health Department doesn’t operate the cannons unless there is a specific complaint in an area where there are lots of birds, Spillman noted. He said so far this year the birds are not as bad as in the past. -
Boil water advisory is lifted countywide
The water controversy that Pulaski County has been boiling over — so to speak — for the last week is finally over.
At 10 minutes after noon Wednesday, the “boil water” advisory for the Western Pulaski Water District was lifted — almost a full week after the problems began around 1 p.m. last Thursday.
Prior to that, the Somerset Water Service — along with the other water providers in its system, including Science Hill Water, Southeastern Water, and Eubank Water — lifted their advisories, with Somerset on Saturday afternoon and the last, Southeastern, by Monday morning. Western Pulaski was the last in the system to complete sample testing for potential contaminants, due to not being able to access its Pikeville-based testing lab until Monday.
Somerset Mayor Eddie Girdler thanked the public for its patience and understanding during the duration of the boil water advisory — put in place to keep citizens from drinking water that could have been contaminated after an accident last Thursday at the water plant site — and also thanked all the city employees for their hard work during this time.
“The boil water advisory went about as well as would be expected,” said Girdler.
- More Local News Headlines






